News

February Rise In Construction Outlays Contrasts With Pandemic-driven Collapse In March As Owners, Government Orders Shut Down Projects

Survey Finds Contractors Face Shortages of Materials and Workers, Delivery Delays and Cancellations;  Association Officials Urge Additional Measures to Help Workers, Firms and the Economy to Recover

Construction spending in February increased 6.0 percent from February 2019, with year-over-year gains in both residential and nonresidential outlays, according to a new analysis of federal data released today by the Associated General Contractors of America. Association officials cautioned that their latest survey shows conditions for contractors have deteriorated rapidly since February. They called on Congress to urgently pass targeted recovery measures to boost infrastructure funding, compensate firms for lost or delayed federally funded work, and provide needed pension relief.

鈥淪pending in February declined 1.3 percent from an upwardly revised, exceptionally strong pace in January that was aided by unusually mild winter weather in much of the country,鈥 said Ken Simonson, the association鈥檚 chief economist. 鈥淭ogether, the rate in the first two months of 2020 represents a high-water mark immediately before government officials ordered widespread business closures and project owners canceled or halted work on their sites. The survey we conducted March 23 to 26 found that 39 percent of the more than 1600 respondents said they had been directed to stop work on one or more projects.鈥

Simonson added that 45 percent of respondents reported experiencing project delays or disruptions. Shortages of material, parts and equipment, including vital personal protective equipment for workers such as respirators, were reported by 23 percent of respondents. Eighteen percent reported shortages of craftworkers, while 16 percent said projects were delayed by shortages of government workers needed for inspections, permits and other actions. Thirteen percent said delay or disruption had occurred because a potentially infected person had visited a jobsite.

鈥淲hen projects shut down, jobs are lost not only in construction but also in a host of other industries, ranging from quarries to manufacturers, and truckers to professional services,鈥 the economist noted. 鈥淚nvesting in infrastructure now will bring these jobs back sooner and will buy a lot more construction while fuel and materials costs are low.鈥

Association officials said that, considering that 39 percent of contractors have had at least one project canceled or delayed because of the coronavirus, construction spending is likely to decline for the foreseeable future. They added that firms will have a hard time continuing to pay current staff under these conditions and called on Washington officials to make new investments in infrastructure, provide relief from losses incurred on delayed or canceled federally funded projects, and pass protections for multi-employer pensions in order to help the industry recover from the economic impacts of the pandemic.

鈥淭he pandemic is prompting a collapse in demand for commercial construction, putting tens of thousands of jobs at risk,鈥 said Stephen E. Sandherr, the association鈥檚 chief executive officer. 鈥淐ongress and the administration must do more to make sure that efforts to flatten the curve don鈥檛 flat-line this industry and its millions of jobs.鈥

View 蜜桔直播鈥檚 coronavirus resources and survey.

Industry Priorities